Peikko Group’s Norwegian subsidiary Peikko Norge AS delivered Rock Anchor Foundation Technology to Tellenes wind park, which is locaded at the Sokndal and Lund municipalities in Rogaland county, south-western part of Norway.

 

Peikko was responsible for the foundation design with the structural calculations and delivered all of the steel components to the 50 wind turbine foundation. The deliveries included  FATBAR® rock anchors, tower adapter plate with tower flange connection bolts, drilling templates- and assembling system, and a special reinforcement steel technology.

The wind park was developed by Zephyr and Norsk Vind Energi, and their project investor is BlackRock. Google has bought the entire 12-year power production of the wind park, to supply their European data centers with renewable energy. The wind park was completed and put into operation in September 2017.

The heavy maschinery contractor Stangeland Maskin AS, was responsible of the civil earthworks and infrastructure. Their subcontractor Skanska AS carried out the technical assembly of steel components and casting works of the Peikko Rock Anchored Foundations. Siemens delivered 50 of their SWT-3.2MW-113 turbines with hub heights of 93 meters.

Peikko delivered FATBAR® Rock Anchors, rock adaptor plates and tower bolts, drilling template- and assembling system, special reinforcement steel technology.

Peikko is also responsible for the structural metrics associated to the design of the Rock Anchor Foundation.

 

Подробнее down-arrow.png

The opening of Tellenes marks a historic day for Norwegian wind power. Within 14 months, the team behind Tellenes have built a power plant the size of the Alta power station, which in it self is an impressive feat. Moreover, with BlackRock as owners, and Google as the PPA off taker, we have now firmly established wind power as an industry for the future in Norway, Isachsen continues.

Øyvind Isachsen, CEO of Norwea

О проекте

Застройщик:
Zephyr AS
Строительная компания:
Stangeland AS / Skanska AS
Проектировщик:
Peikko is also responsible for the structural associated to the design of the Rock Anchor Foundation
Дата поставок:
2016-2017
Год завершения строительства:
2017
Количество турбин:
50
Производитель турбин:
Siemens
Мощность турбины, МВт:
WT-3.2MW-113
Высота, м:
93